Language Arts Complex - Measure M:
Construction activity on the interior is nearly complete. Furniture deliveries are ongoing. Exterior finishing continues with metal panel installation. Site work continues with installation of irrigation lines and landscaping. The work on the access road between the Math & Science bldg. and the LRC has been completed. Passage from the LRC to the Bookstore is now open via the sidewalks on the north side of the new Language Arts Complex building. Construction fences are starting to be removed and will be repositioned periodically throughout the week to accommodate site work. Exercise caution around construction vehicles and areas surrounding the construction site. Noise level will be low for these activities. (See attached map [PDF] for work areas and construction vehicle routes)
GenEd Bldg Demo Project:
The demolition of the General Education building on campus continues in its early phase with abatement activity. There will be increased construction vehicle activity around the building this week that may impact the access road north of the GenEd bldg. Extra care should be taken on this access road and around this building. Please watch for and steer clear of areas with caution tape. Noise level will be low to moderate for these activities. (See attached map [PDF] for work area)
Restroom Remodel Project - Campus:
Older restrooms throughout campus are being remodeled. Currently, the restrooms at the Theater (between the Theater and Music bldg.) are closed. The nearest available restrooms are in the Student Services Center, and at the Fine Arts building. Noise level will be low for these activities. (See attached map [PDF] for work area)
Painting / RecEd Building - Campus:
Painting of the Recreation Education building has been completed.
Nursing Building - Campus:
Renovation in the Nursing building has been completed.
Site Restoration Project - Campus:
Restoration of the old KOCE building demolition site located on the east side of campus between the Amphitheater and Fine Arts, north of Forum 2 continues. Contractors with trucks and equipment will be entering and exiting the site from the east parking lots off of Gothard St. via the access roads north and south of the Amphitheater. Please use caution in and around these areas and mind the flagmen when vehicles are maneuvering. The site will remain fenced off with no public access within the fence. Noise level will be low for these activities. (See attached map [PDF] for work area)