Construction Update for Week Beginning: 2/12/24

Language Arts Complex - Measure M:
The new Language Arts Complex is nearing completion and the building is open for classes.  Preparation for the commissioning of the building continues.  Noise level will be low for these activities. 

GenEd Bldg Demo Project - Campus and Measure M:
Demolition of one remaining building and the surrounding area has been set back due to recent rains.  Expected demo completion has been moved to the end of February 2024, still dependent upon future rain and sufficient drying of the soil. The new landscaping is expected to be in place by the end of the spring 2024 semester.  Construction vehicle activity will impact the parking lot near Auto Tech and the Native Garden, and the access road along Auto Tech, north of the site.  Extra care should be taken along the access road.  There is no pedestrian access within the construction fence.  Noise level will be low to moderate for these activities.  (See attached map [PDF] for work area and construction vehicle routes)

Handrail Installation Project - Campus:
The handrail at the southwest corner of campus outside the Public Safety Bldg. is forthcoming.  Please watch for and avoid the area once work is in progress and mind caution tape and barricades.  Noise level will be low to moderate for this activity. (See attached map [PDF] for work area)

Underground Electrical - Campus:
Contractors will continue inspecting electric cables via manholes throughout campus this week.  Please watch for delineators and avoid open manholes.  Noise level will be low for this activity.

General Note:
For any additional questions or clarifications, please email Mike Golden at mgolden7@gwc.cccd.edu for Measure M projects, and Frank Fonseca at ffonseca1@gwc.cccd.edu or Joe Dowling at jdowling@gwc.cccd.edu for Campus projects.